URGENT ACTION NEEDED
According to the Agenda Package
released on the County website on Wednesday, County Council will make a
decision on the scope & cost of the proposed new Leslieville Fire
Hall on Tuesday, June 9.
Current plans suggest either a
5 bay (10,000 sq. ft.) or 3 bay (6,000 sq. ft.) apparatus storage area
with an additional 6,000 sq. ft. staff area. Cost of building a 16,000
sq. ft. facility is $2,900,000 or $181.25 per sq. ft.
County staff has noted that a 3 bay facility is sufficient. This would provide a saving of $725,000.
Research indicates that only 1500 sq. ft. of staff space is needed for
11-20 full time employees. There are currently 11 on-call volunteer
fire fighters at Leslieville. NO NEED FOR 6,000 SQ. FT. OF STAFF SPACE.
Cutting the unnecessary 4500 sq. ft. would save an additional $815,
625. (Note: The new facility at Condor already has 6,000 sq. ft. of
staff space and the two groups meet there regularly to train. There is
no need for the additional space at Leslieville.)
TOTAL
SAVING TO BE REALIZED WITH A 3 BAY FACILITY AND 1500SQ. FT. OF STAFF
SPACE IS $1,540,625 OR 33% OF THE CURRENT PROJECTED $4,671,250. WHO
WOULD IGNORE A SAVING OF 33%, ESPECIALLY IN THESE QUESTIONABLE ECONOMIC
TIMES???
Fiscal responsibility is even more important
now. There is no justification for over-spending on unnecessary,
over-built, under-used space.
JOIN THE SOS PROTEST--- Stop Over Spending
LET YOUR VOICE BE HEARD